There are no persons interested in building of the access roads to the Kerch bridge. Contest failed

Terms of the realization of the project of Kerch bridge in occupied Crimea from Russia could remove, because the second contest to choose prime contractor to build railway access to the object has failed. There are no persons interested in the building of them. Kommersant newspaper writes about it.

This is about competition to develop working documents and build railway access to Kerch bridge. The price of the contract is $250 815 840, the period of execution – November 2019. Only one application was submitted from JSC ‘Railway roads of Yakutia’, but company hasn’t passed prequalification selection.

We add that access to the bridge must be built to November 2019 for $250 815 840, but representatives of the branch consider this price low.

If contest doesn’t take part at the first quarter of 2017, the ‘administrative decisions’ will be needed, analysts are noting.

Погода
Погода в Киеве

влажность:

давление:

ветер: